Re: Routing should be consider for costing purpose only

$
0
0

Dear Ozgen canan,

 

Yesterday i have achieved this by maintaining settings for both planned orders and production orders i.e . OPU3 and OPU5 -2- Do not adjust basic dates. (but its generating schd.dates confusing to user) and also If we not maintaining OPU5 its changing planned order dates based on production dates in case of partial conversion

 

 

 

Regards

Satya