Hi,
You wont get any standard report for the above requirement, follow the below process to achieve your requirement.
As per your requirement you need to get all BOM components quantity for a particular FG material. So itemization of FG.
To meet the above requirement you need to pass the material and plant in KEKO table, get the cost estimate number. Pass the cost estimate number in CKIS table.
In this table you will get the all components (BOM and Routing) with quantity, but after that you need to do the remaining calculations in excel.
Please precede the above process and let me know if you need any further help.
Regards,