Re: SAP PS-PM Integration to capture maintenance order cost at Internal Activity

$
0
0

Hi Ashely,

Maintenance related to projects shall be maintained through PM-PS integration.

Here maintenance orders will carry the cost and will be settled to project WBS.

Budget control shall be maintained at these WBS.

Maintenance Orders shall be assigned to corresponding WBS / Network.

Here may use PM/PS reff. element also.

For this you need to maintain few settings at network level as mentioned above.

Regards,

VINOD.V